GS IAS Logo

< Previous | Contents | Next >

8.3 COMPONENTS OF EIA

The difference between Comprehensive EIA and Rapid EIA is in the time-scale of the data supplied. Rapid EIA is for speedier appraisal process. While both types of EIA require inclusion/ coverage of all significant environmental impacts and their mitigation, Rapid EIA achieves this through the collection of one season (other than monsoon) data only to reduce the time required where comprehensive EIA collects data from all four seasons.

Rapid EIA is acceptable if it does not compromise on the quality of decision-making. The review of Rapid EIA submissions will show whether a comprehensive EIA is warranted or not.

It is, therefore, clear that the submission of a professionally prepared Comprehensive EIA in the first instance would generally be the more efficient approach. Depending on nature, location and scale of the project EIA report should contain all or some of the following components.


 

Air EnvironmentNoise EnvironmentWater EnvironmentBiological EnvironmentLand EnvironmentSocio-economic and Health EnvironmentRisk AssessmentEnvironment Management Plan